.. _merge_duty:

Merge Duty
==========

All code changes to Firefox land in the
`mozilla-central <https://hg.mozilla.org/mozilla-central>`__ repository

* The ``nightly`` releases are built from that repo twice a day.
* DevEdition and Beta releases are built from the `beta <https://hg.mozilla.org/releases/mozilla-beta/>`__ repository
* Extended Support Releases follow-up from the relevant ESR repo, such as `mozilla-esr115 <https://hg.mozilla.org/releases/mozilla-esr115/>`__
* Release and Release Candidates are built from `mozilla-release <https://hg.mozilla.org/releases/mozilla-release/>`__ repository

How are those repositories kept in sync? That's ``MergeDuty`` and is
part of the ``releaseduty`` responsibility.

Overview of Procedure
---------------------

``MergeDuty`` consists of multiple separate days of work. Each day you
must perform several sequential tasks. The days are spread out over
nearly three weeks, with *three* major days of activity:

-  Do the prep work a week before the merge

   -  `Do migration no-op trial runs <#do-migration-no-op-trial-runs>`__ (2 min of action, 15 min of wait)

-  On Merge day:

   -  `Merge beta to release <#merge-beta-to-release>`__ (2 min of action, 20 min of wait)
   -  `Reply migrations are
      complete <#reply-to-relman-migrations-are-complete>`__ (1 min)

-  A week after Merge day, bump mozilla-central / the `main` branch:

   -  `Merge main to beta <#merge-main-to-beta>`__ (2 min of action, 20 min of wait)
   -  `Re-open trees <#re-opening-the-trees>`__ (2 min)
   -  `Verify the l10n bumper output <#verify-the-l10n-bumper-output>`__ (2 min)
   -  `Tag main and bump versions <#tag-main-and-bump-versions>`__ (2 min of action, 15 min of wait)
   -  `Bump mozilla-esr <#bump-esr-version>`__ (In parallel, 2 min of action, 15 min of wait)
   -  `Reply to RelMan that procedure is
      completed <#reply-to-relman-central-bump-completed>`__ (1 min)
   -  `Update wiki versions <#update-wiki-versions>`__ (2 min)

Historical context of this procedure:

Originally, the ``m-c`` -> ``m-b`` was done a week after ``m-b`` ->
``m-r``. Starting at ``Firefox 57``, Release Management wanted to ship
DevEdition ``b1`` week before the planned mozilla-beta merge day. This
meant Releng had to merge both repos at the same time. With 71.0, we're
back to the initial workflow with merging ``m-b`` -> ``m-r`` in the
first week and then ``m-c`` -> ``m-b`` in the follow-up week.

Do the prep work a week before the merge
----------------------------------------

Do migration no-op trial runs
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Doing a no-op trial run of each migration has one major benefit these
days: you ensure that the migrations themselves work prior to Merge day.

General steps
^^^^^^^^^^^^^

1. Go to
   `Treeherder <https://treeherder.mozilla.org/>`__.
2. Select the repo depending on the merge you want to perform (central, beta or the ESR one).
3. On the latest push, click on the down arrow at the top right corner.
4. Select “Custom push action…”
5. Choose ``merge-automation`` from the dropdown and paste the payload provided in the sections below.
6. In Treeherder, you'll see a new push show up in Treeherder in the repo you will be merging to. It can take a few minutes for the push and task to appear.
7. Click on the merge or bump tasks (not the Gecko decision task). A job details panel will pop up and from there you'll find a link to the diff file in the artifacts tab. Note: There will be a cron job that kicks off another bump task with same th name, only one of them will contain the diff.


mozilla-beta->mozilla-release migration no-op trial run
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

1. Follow the `general steps <#general-steps>`__ hopping on `beta <https://treeherder.mozilla.org/#/jobs?repo=mozilla-beta>`__
2. Insert the following payload and click trigger.

.. code:: yaml

   force-dry-run: true
   behavior: beta-to-release

mozilla-central->mozilla-beta migration no-op trial run
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

1. Follow the `general steps <#general-steps>`__ hopping on `central <https://treeherder.mozilla.org/#/jobs?repo=mozilla-central>`__
2. Insert the following payload and click trigger.

.. code:: yaml

   force-dry-run: true
   behavior: main-to-beta

mozilla-esr bump no-op trial run
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

mozilla-esr branches evolve over time: Today (August 2023), mozilla-esr115 is
the current esr, and that is used in the discussion below; in the future, you
may need to substitute a different esr version number.

1. Follow the `general steps <#general-steps>`__ hopping on `esr115 <https://treeherder.mozilla.org/#/jobs?repo=mozilla-esr115>`__
2. Insert the following payload and click trigger.

.. code:: yaml

   force-dry-run: true
   behavior: bump-esr115

Diff should be similar to
`this esr115 one <https://hg.mozilla.org/releases/mozilla-esr115/rev/6a58ffb58ea554fd3a1c2276e5f9205a0e5c6bec>`__.


Release Merge Day - part I
--------------------------

**When**: Wait for go from relman to release-drivers@mozilla.org. Relman
might want to do the migration in two steps. Read the email to
understand which migration you are suppose to do, and then wait for
second email. For date, see `Release Scheduling
calendar <https://calendar.google.com/calendar/embed?src=bW96aWxsYS5jb21fZGJxODRhbnI5aTh0Y25taGFiYXRzdHY1Y29AZ3JvdXAuY2FsZW5kYXIuZ29vZ2xlLmNvbQ>`__
or check with relman

Merge beta to release
~~~~~~~~~~~~~~~~~~~~~

1. `Close
   mozilla-beta <https://lando.services.mozilla.com/treestatus/mozilla-beta/>`__.
   Check *“Remember this change to undo later”*. Please enter a good
   message as the reason for the closure, such as “Mergeduty - closing
   beta for $VERSION RC week”. Note: You need to be in the `treestatus_users group <https://people.mozilla.org/a/treestatus_users/>`__
   in order to change trees.
2. Run the ``m-b -> m-r`` `no-op trial
   run <#do-migration-no-op-trial-runs>`__ one more time, and show the
   diff to another person on releaseduty.
3. The diff for ``release`` should be fairly similar to
   `this <https://hg.mozilla.org/releases/mozilla-release/rev/f061d37ca7aea8d05d976908e376e649257f2151>`__,
   with updated the version change.
4. Submit a new task with ``force-dry-run`` set to false:

.. code:: yaml

   force-dry-run: false
   behavior: beta-to-release

:warning:
   It's not unlikely for the push to take between 10-20 minutes to complete.

:warning:
   If an issue comes up during this phase, you may not be able to run
   this command (or the no-op one) correctly. You may need to publicly
   backout some tags/changesets to get back in a known state.

1. Upon successful run, ``mozilla-release`` should get a version bump
   and branding changes consisting of a ``commit`` like
   `this <https://hg.mozilla.org/releases/mozilla-release/rev/118aa10ac456d05606f113ade5c26ae4637081ce>`__
   and two new tags. The first tag should be
   `in the form FIREFOX_RELEASE_xxx_END <https://hg.mozilla.org/releases/mozilla-release/rev/92e4f64aabfb73736f7e2486802d8deb54dbf111>`__
   - where the xxx is the major Gecko version that Release had prior to the merge. The other tag
   should be
   `in the form FIREFOX_RELEASE_yyy_BASE <https://hg.mozilla.org/releases/mozilla-release/rev/c4ed5781ba9260b6a46b97be4c66f32a28eea1a6>`__
   - where the yyy is the major Gecko version that Release now has.

2. At the same time ``mozilla-beta`` should get a tag
   `in the form FIREFOX_RELEASE_yyy_BASE <https://hg.mozilla.org/releases/mozilla-beta/rev/c4ed5781ba9260b6a46b97be4c66f32a28eea1a6>`__
   - where the yyy is the major Gecko version that Release now has. (This should be
   the exact same tag and revision as the second one that you saw in the Release repo in step 1.)
3. Verify changesets are visible on `hg
   pushlog <https://hg.mozilla.org/releases/mozilla-release/pushloghtml>`__
   and
   `Treeherder <https://treeherder.mozilla.org/#/jobs?repo=mozilla-release>`__.
   It may take a couple of minutes to appear.

:warning:
   The decision task of the resulting pushlog in the ``mozilla-release``
   might fail in the first place with a timeout. A rerun might solve
   the problem which can be caused by an unlucky slow instance.

Reply to relman migrations are complete
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Reply to the migration request with the template:

.. code:: text

   This is now complete:
   * mozilla-beta is merged to mozilla-release
   * mozilla-release is tagged and version bumped to XX.Y
   * beta will stay closed until next week

Release Merge Day - part II - a week after Merge day
----------------------------------------------------

**When**: Wait for go from relman to release-drivers@mozilla.org. For
date, see `Release Scheduling
calendar <https://calendar.google.com/calendar/embed?src=bW96aWxsYS5jb21fZGJxODRhbnI5aTh0Y25taGFiYXRzdHY1Y29AZ3JvdXAuY2FsZW5kYXIuZ29vZ2xlLmNvbQ>`__
or check with relman

Merge main to beta
~~~~~~~~~~~~~~~~~~~~~

1. Run the ``m-c -> m-b`` `no-op trial
   run <#do-migration-no-op-trial-runs>`__ one more time, and show the
   diff to another person on releaseduty.
2. The diff generated by the task should be fairly similar to
   `this <https://hg.mozilla.org/releases/mozilla-beta/rev/a724e117199b2bb42ece67dc0017f1b6cbf493df>`__.
3. Submit a new task with ``force-dry-run`` set to false:

.. code:: yaml

   force-dry-run: false
   behavior: main-to-beta

:warning:
   It's not unlikely for the push to take between 10-20 minutes to complete.

1. Upon a successful run, ``mozilla-beta`` should get a version bump and
   branding changes consisting of a ``commit`` like
   `this <https://hg.mozilla.org/releases/mozilla-beta/rev/a724e117199b2bb42ece67dc0017f1b6cbf493df>`__
   and two new tags. One tag should be
   `in the form FIREFOX_BETA_xxx_END <https://hg.mozilla.org/releases/mozilla-beta/rev/789d06370703ec8dd4ce462a549390adf586a81a>`__
   - where xxx is the major Gecko version that Beta had prior to the merge. The other tag should be
   `in the form FIREFOX_BETA_yyy_BASE <https://hg.mozilla.org/releases/mozilla-beta/rev/592c2df16ac45a09c837b8a281e366c419c8b94d>`__
   - where yyy is the major Gecko version that Beta now has.

   Click the first HG revision link (left side under date and timestamp) for the merge push to verify this.
2. Verify that ``browser/locales/l10n-changesets.json`` has revisions, not
   ``default``, and/or verify that the merge task has l10n-bump in the logs. You'll need to click on the second HG revision link (commit message will be something like ``"no bug - Bumping Firefox |10n..."``) to verify this.
   The diff should look like `this
   <https://hg.mozilla.org/releases/mozilla-beta/rev/5f344535f8a3340fa51528be88e7104538b64b2e>`__
3. At the same time ``mozilla-central`` should get a new tag
   `in the form FIREFOX_BETA_yyy_BASE <https://hg.mozilla.org/mozilla-central/rev/592c2df16ac45a09c837b8a281e366c419c8b94d>`__
   - where yyy is the major Gecko version that Beta now has.
   (This should be the exact same tag and revision as the second one that you saw in the Beta repo
   in step 1.) It's worth noting that we do not create `FIREFOX_NIGHTLY_yyy_BASE` tags, as we do
   for Beta & Release repositories.
4. Verify changesets are visible on `hg
   pushlog <https://hg.mozilla.org/releases/mozilla-beta/pushloghtml>`__
   and
   `Treeherder <https://treeherder.mozilla.org/#/jobs?repo=mozilla-beta>`__.
   It may take a couple of minutes to appear.

:warning:
   The decision task of the resulting pushlog in the ``mozilla-beta``
   might fail in the first place with a timeout. A rerun might solve
   the problem which can be caused by an unlucky slow instance.

:warning:
   The merge day automation may not be idempotent.
   The merge automation task may fail and auto-retry (because of a worker shutdown, for instance).
   If the task retries after updating the state of the repo, it will update the state of the repo again, pushing repeated commits.

Re-opening the tree(s)
~~~~~~~~~~~~~~~~~~~~~~

`Restore mozilla-beta tree <https://lando.services.mozilla.com/treestatus/mozilla-beta/>`__
to its previous state (`approval-required`) so that **l10n bumper can run**.

Tag main and bump versions
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

**What happens**: A new tag is needed to specify the end of the nightly
cycle. Then clobber and bump versions in ``mozilla-central`` as
instructions depict.

1. Follow the `general steps <#general-steps>`__
2. Insert the following payload and click submit.

.. code:: yaml

   force-dry-run: false
   behavior: bump-main

1. Upon successful run, ``mozilla-central`` should get a version bump
   consisting of a ``commit`` like
   `this <https://hg.mozilla.org/mozilla-central/rev/d42e0ca4bb3e3d7fa475687da045300b07a20db1>`__
   and a new tag
   `in the form FIREFOX_NIGHTLY_xxx_END <https://hg.mozilla.org/mozilla-central/rev/ffc39a5fbec9708c375cd9a6b978900f9f1b7b74>`__
   - where xxx is the major Gecko version that mozilla-central had prior to the version bump.
2. Verify changesets are visible on `hg
   pushlog <https://hg.mozilla.org/mozilla-central/pushloghtml>`__ and
   `Treeherder <https://treeherder.mozilla.org/#/jobs?repo=mozilla-central>`__.
   It may take a couple of minutes to appear.

Bump ESR version
~~~~~~~~~~~~~~~~

Note: You could have one ESR to bump, or two. If you are not sure, ask.

Run the bump-esr `no-op trial run <#do-migration-no-op-trial-runs>`__
one more time, and show the diff to another person on releaseduty.

Diff should be similar to `this
one <https://hg.mozilla.org/releases/mozilla-esr115/rev/6a58ffb58ea554fd3a1c2276e5f9205a0e5c6bec>`__.

Push your changes generated by the no-op trial run:

1. Follow the `general steps <#general-steps>`__
2. Insert the following payload and click submit.

.. code:: yaml

   force-dry-run: false
   behavior: bump-esr115

*Note* The esr version is currently hardcoded to the action; If necessary, an action for other esr
versions can be added to ``taskcluster/ci/config.yml``.

1. Upon successful run, ``mozilla-esr${VERSION}`` should get a
   ``commit`` like
   `this <https://hg.mozilla.org/releases/mozilla-esr115/rev/6a58ffb58ea554fd3a1c2276e5f9205a0e5c6bec>`__.
2. Verify new changesets popped on
   https://hg.mozilla.org/releases/mozilla-esr115/pushloghtml

Reply to relman central bump completed
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Reply to the migration request with the template:

.. code:: text

   This is now complete:
   * mozilla-central is merged to mozilla-beta
   * mozilla-central is tagged and version bumped to XXX.0a1
   * mozilla-beta is tagged and version bumped to YYY.0b1
   * mozilla-esr115 is version bumped to ZZZ.A.0esr
   * newly triggered nightlies will pick the version change on cron-based schedule

Hint: verify current versions

   - `central <https://hg.mozilla.org/mozilla-central/file/default/browser/config/version_display.txt>`__
   - `beta <https://hg.mozilla.org/releases/mozilla-beta/file/default/browser/config/version_display.txt>`__
   - `esr115 <https://hg.mozilla.org/releases/mozilla-esr115/file/default/browser/config/version.txt>`__

Update wiki versions
~~~~~~~~~~~~~~~~~~~~

1. Edit the new values manually: (ok to update a day early)

-  `NEXT_VERSION <https://wiki.mozilla.org/Template:Version/Gecko/release/next>`__
-  `CENTRAL_VERSION <https://wiki.mozilla.org/Template:Version/Gecko/central/current>`__
-  `BETA_VERSION <https://wiki.mozilla.org/Template:Version/Gecko/beta/current>`__
-  `RELEASE_VERSION <https://wiki.mozilla.org/Template:Version/Gecko/release/current>`__
-  `Next release
   date <https://wiki.mozilla.org/index.php?title=Template:NextReleaseDate>`__.
   This can be found in the `release calendar
   <https://wiki.mozilla.org/Release_Management/Calendar>`__. This updates

   -  `The next ship
      date <https://wiki.mozilla.org/index.php?title=Template:FIREFOX_SHIP_DATE>`__
   -  `The next merge
      date <https://wiki.mozilla.org/index.php?title=Template:FIREFOX_MERGE_DATE>`__
   -  `The current
      cycle <https://wiki.mozilla.org/index.php?title=Template:CURRENT_CYCLE>`__

Do a manual check of product-details after the Nightly version bump
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
When Nightly builds with a new version number are uploaded to the Mozilla archive,
the Nightly version in ShipIt is automatically updated. When the version is updated,
a message is sent to `#releaseduty <https://matrix.to/#/#releaseduty:mozilla.org>`__:

::

   taskcluster-firefoxci
   sheriffduty: ciduty: releaseduty: Updated firefox nightly version to `130.0a1`.

The product-details API should be updated automatically, but sometimes messages are dropped,
or intermittent errors keep the API from being updated.
It is a good idea to check https://product-details.mozilla.org/1.0/firefox_versions.json
and make sure ``FIREFOX_NIGHTLY`` is set to the current value.
If it is not, manually trigger a product-details rebuild from the ShipIt admin UI.

Release Merge Day - part III - release day
------------------------------------------

Historical issues
-----------------

The merge day automation may not be idempotent
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
The merge automation task may fail and auto-retry (because of a worker shutdown, for instance).
If the task retries after updating the state of the repo, it will update the state of the repo again, pushing repeated commits.